How the city built libraries at $930 psf … and years behind schedule

Under bureaucratic city design agency, the construction costs doubled

TRD NEW YORK /
Apr.April 10, 2017 03:20 PM

Hunter’s Point Library (Credit: NYC Dept. of Design & Construction)

A city agency designed to streamline capital projects actually doubled the cost of new libraries and cultural centers between 2010 and 2014, according to a new report.

The Center for an Urban Future, a nonpartisan think tank, just released a report that shows that the median cost of construction for these projects, when managed by the city’s Department of Design and Construction (DDC), was $930 per square foot, the Wall Street Journal reported. The New York Building Congress estimates that speculative office construction usually runs between $425 to $500 per square foot. The median duration of these projects is seven years.

“What starts out as a well-intentioned goal of saving the city some money, I think ends up costing the city money and significantly delaying the process,” Jonathan Bowles, executive director of the Center for an Urban Future, told the Journal.

The extra costs stem from the fact that these projects are subject to many additional reviews and approvals. Even small changes to these projects require approval from the city’s Office of Management and Budget, for example. Representatives for the DDC and Office of Management and Budget told the Journal that the department has improved since 2014. [WSJ] — Kathryn Brenzel 


Related Articles

arrow_forward_ios
US Steel’s sprawling South Works site is about the size of Downtown Chicago. At left, Common, who wants to partner with developers on a mixed-use entertainment district there, and Dan McCaffery, whose vision for a 13,000-home community fizzled out. (Credit: Common by Paras Griffin/Getty Images; McCaffery via McCaffery Interests; aerial by Cushman & Wakefield)

South Works, the 415-acre “magnificent property,” is Chicago’s biggest development opportunity

Miki Naftali, Steven Witkoff and Ryan Freedman

TRD Talks: How developers are contending with coronavirus

Mayor Bill de Blasio halted ULURP, stalling projects like 960 Franklin Avenue, Rikers Island and Industry City 

These projects could be held up by New York’s rezoning freeze

Morris Moinian and 1150 6th Avenue (Credit: Noam Galai/Getty Images, Google Maps)

Morris Moinian to sell site of stalled hotel project

An aerial of Flushing's waterfront and New York City Council member Peter Koo (Credit: Google Maps)

Massive Flushing waterfront development stirs opposition

133-25 37th Avenue in Flushing

Developer Gary Tsan buys Flushing property for $60M

South Carolina town puts moratorium on development (Credit: iStock)

The high cost of low taxes: South Carolina town bans all development for 16 months

U.S. Rep. Alexandria Ocasio-Cortez and Sunnyside Yards (inset) (Credit: Getty Images and Wikipedia)

AOC resigns from Queens megadevelopment steering committee

arrow_forward_ios
Loading...