Two Bridges developers plan to contest judge’s ruling against plans for LES mega development

Judge Arthur Engoron is sending the Two Bridges towers to ULURP

New York /
Aug.August 02, 2019 09:30 AM
Supreme Court Judge rules against LES development

Supreme Court Judge rules against LES development

Citing a book that laments the “proliferation of skyscrapers” during the turn of the 20th century, Supreme Court Judge Arthur Engoron spoiled the plans of Two Bridges tower developers CIM Group, L+M Development Partners, Starrett Development and JDS Development Group — for now.

Judge Engoron enjoined the Department of Buildings from issuing permits until the project is properly approved, according to a press release, after temporarily halting the development in June. In a statement, a spokesperson for the joint venture said the developers plan to fight the ruling, The City reported.

The developers planned to erect four 60 to 100-story towers with 2,775 apartments, with 25 percent of the units set aside as affordable. The plans had been previously approved, but the Department of City Planning voted to change the development sites’ permit without going through a public review. Now, the towers may be headed to Uniform Land Use Review Procedure (ULURP), a community review process that could stretch on for months.

Two more lawsuits have challenged the Two Bridges development, by community groups including Good Old Lower East Side and CAAAV Organizing Asian Communities. A representative from CAAV said that the ruling gives them time to work on their larger goal of limiting building heights across the board on the Lower East Side.

[The City] — Georgia Kromrei


Related Articles

arrow_forward_ios
Ron Moelis, CFO and Founding Partner at L+M, and David Thompson, CFO and Principal at CIM, with the Two Bridges project (L+M, CIM, SHoP Architects)
CIM Group, L+M Development file plans for 1.3M sf Two Bridges tower
CIM Group, L+M Development file plans for 1.3M sf Two Bridges tower
JDS founder Michael Stern and US Crane & Rigging LLC Owner Thomas Auringer with the complaint and 111 W. 57th Street (Supreme Court of New York, 111 W 57, Facebook via Auringer)
Michael Stern’s JDS sues crane company at 111 West 57th Street for $50M
Michael Stern’s JDS sues crane company at 111 West 57th Street for $50M
JDS Development's Michael Stern and 613 Baltic Street (JDS, VOA Architecture)
Michael Stern-owned condo project files for Chapter 11 bankruptcy
Michael Stern-owned condo project files for Chapter 11 bankruptcy
JDS Development's Michael Stern and 111 West 57th Street (JDS)
JDS sues 111 West 57th contractor, insurer over shoddy work and “blunderbuss requests”
JDS sues 111 West 57th contractor, insurer over shoddy work and “blunderbuss requests”
L+M Development Partners' Ron Moelis and a rendering of Sendero Verdo (Photos via L+M; Handel Architects)
L+M in deal with union laborers to cut wages on affordable projects
L+M in deal with union laborers to cut wages on affordable projects
Related chairman Stephen Ross and 265-475 Cherry Street (Getty; Google Maps)
Related to buy Section 8 buildings for $435M
Related to buy Section 8 buildings for $435M
WATCH: JDS’ Stern and SHoP’s Pasquarelli on shaping the skyline
WATCH: JDS’ Stern and SHoP’s Pasquarelli on shaping the skyline
WATCH: JDS’ Stern and SHoP’s Pasquarelli on shaping the skyline
JDS Development Group's Michael Stern
5 things to know about supertall condo developer Michael Stern
5 things to know about supertall condo developer Michael Stern
arrow_forward_ios

The Deal's newsletters give you the latest scoops, fresh headlines, marketing data, and things to know within the industry.

Loading...