Midtown parking garage partially collapses

The vacant five-story structure on 38th Street is the second collapse in the last week

TRD New York /
Jul.July 08, 2020 01:45 PM
205 East 38th Street (Twitter/FDNY)

205 East 38th Street (Twitter/FDNY)

UPDATED, July 8, 2020, 2:59 p.m.: A five-story parking garage in Murray Hill partially collapsed on Wednesday afternoon.

A spokesperson for the city’s Department of Buildings said its inspectors “were called to the scene at 205 East 38th Street, Manhattan, to investigate reports of a partial façade collapse.” The  inspectors found that a 45-by-10-foot section of bricks collapsed from the parapet level of the garage’s façade onto the sidewalk.

The agency said one injury was reported and two parked cars were damaged by the falling bricks.

The DOB ordered the property owner — which records show is Antarctica Infrastructure Partners — to immediately install a sidewalk shed. The agency’s investigation is still ongoing.

Antarctica did not immediately respond to a request for comment.

The property was issued a violation in September 2019 for failing to correct defects in the elevator, according to DOB’s website. The building currently has seven open violations related to the elevator.

The collapse is the second to rock New York City in the last week. A building that housed a Body Elite Gym collapsed in Brooklyn last week, injuring no one.

A partial stop-work order had been issued at the Brooklyn property, because a brick wall was “dangerously bulging” over the sidewalk, according to the DOB. That building had violations related to cracks in the building’s facade in November 2019. Agency inspectors and engineers are investigating the cause of that collapse.


Related Articles

arrow_forward_ios
348 Court Street (Photo by Justin Heiman/Getty Images)

Collapses raise questions about safety-law exemption

Collapses raise questions about safety-law exemption
Clockwise from the top: Dov Hertz and Sunset Industrial Park at 75-81 20th Street in Brooklyn; 155 West 29th Street and 1640 Flatbush Avenue in Brooklyn (Credit: Google Maps; 1640 Flatbush via S9 Architecture)

Worst month of the year for big construction filings

Worst month of the year for big construction filings
204 Bedford Avenue (Citizen App, iStock)

East Village facade plunges to street, Brooklyn building falls during storm

East Village facade plunges to street, Brooklyn building falls during storm
Navillus president Donal O’Sullivan (Image via Navillus)

Navillus CEO, sister arrested in $1M scheme to cheat unions

Navillus CEO, sister arrested in $1M scheme to cheat unions
731 Lexington Avenue (Google Maps)

Former Turner Construction exec pleads guilty in bribery scheme

Former Turner Construction exec pleads guilty in bribery scheme
Javits Center (Google Maps)

Javits worker: I reported discrimination — and was fired

Javits worker: I reported discrimination — and was fired
Social Construct CEO Ben Huh, The Real Deal's Hiten Samtani and Social Construct cofounder Michael Yarne

How code could make multifamily construction more predictable

How code could make multifamily construction more predictable
Social Construct CEO Ben Huh, The Real Deal's Hiten Samtani and Social Construct cofounder Michael Yarne

The REInterview: Social Construct’s founders on making multifamily construction an assembly line

The REInterview: Social Construct’s founders on making multifamily construction an assembly line
arrow_forward_ios

The Deal's newsletters give you the latest scoops, fresh headlines, marketing data, and things to know within the industry.

Loading...