The Real Deal Miami

Hunt Construction withdraws from Miami Beach convention center project

Clark Construction last remaining qualified bidder for $500M project

January 23, 2015 04:01PM
By Katherine Kallergis

  • Print
Miami Beach Convention Center rendering

Miami Beach Convention Center rendering

Hunt Construction Company formally withdrew its bid for the $500 million renovation and expansion of the Miami Beach convention center, The Real Deal has learned.

In a memo obtained by TRD from Miami Beach City Manager Jimmy Morales to Mayor Philip Levine and the city commission, Morales said the withdrawal leaves the city with one qualified bidder, Clark Construction Group.

In November, the commission approved  Clark, Hunt and Hensel Phelps Construction Company, in that order, as the candidates to move to second round in the selection process. Morales had recommended the short list, in line with a selection committee’s ranking.

Miami-based Hunt Construction has completed 20 convention centers and hotel convention center projects, totaling more than $5 billion, according to Miami Beach documents. Bethesda, Maryland-based Clark Construction, the remaining qualified bidder, has completed 15 convention center projects totaling $4.7 billion.

  • Jake

    Lol who just drops out of a 500mm project ???? Very fishy