Stalled crane inspections could freeze projects

New York /
Mar.March 24, 2008 05:13 PM

Construction industry officials say several high-rise projects could be frozen and hundreds of workers could be laid off if a city moratorium on the assembly of high-rise cranes continues beyond next week.

Several construction industry members said that following the March 15 crane collapse on Manhattan’s East Side that killed seven people, the city Department of Buildings has frozen inspections of crane “jumping,” the process of adding sections to a crane so it can reach higher as new buildings progress.

Without a higher crane, the highly choreographed building construction process eventually grinds to a halt.

Alfred Gerosa, chairman of the executive committee of the Cement League, an association of cement contractors, said a contractor on a project on West 42nd Street would lay off 300 workers if a crane is not assembled next week.

“It is no doubt going to have an effect on the economy and men’s pockets,” Gerosa said.

“We realize the urgency of the problem and we recognize we had a very serious accident … (but) if this goes on much longer, maybe as many as seven jobs, which would be about 1,000 workers,” would be halted, he said.

He said there was another job on 91st Street that needed to erect a crane this week that was awaiting inspection.

Louis Coletti, president and chief executive officer of the Building Trades Employers Association, an association of unionized construction firms, said industry representatives were in negotiations with the city to develop tighter standards for crane assembly before work starts again.

He said that the city would likely require engineers who review crane assembly plans to do so a second time instead of only once before an inspector comes to the site, among other changes.

“They are trying to lift [the moratorium] this week,” he said.

About 250 cranes are in operation in the city, he said.

Some firms have not yet been affected by the moratorium. Charles F. Murphy, senior vice president and general manager for Turner Construction Co. in New York said the inspection freeze has not yet had an impact on its projects.

The Department of Buildings did not respond to requests for comment.


Related Articles

arrow_forward_ios
(Image by Wolfgang & Hite via Dezeen)
Hudson Yards megadevelopment inspires a new line of sex toys
Hudson Yards megadevelopment inspires a new line of sex toys
Cammeby's International Group founder Rubin Schron and, from top: 194-05 67th Avenue, 189-15 73rd Avenue and 64-05 186th Lane (Credit: Google Maps)
Ruby Schron lands $500M refi for sprawling Queens apartment portfolio
Ruby Schron lands $500M refi for sprawling Queens apartment portfolio
Wendy Silverstein (Credit: Getty Images)
Wendy Silverstein, co-head of WeWork’s real-estate fund, is out
Wendy Silverstein, co-head of WeWork’s real-estate fund, is out
eXp CEO Glenn Sanford (eXp, iStock)
Virtual broker eXp Realty has another record quarter
Virtual broker eXp Realty has another record quarter
Ira Drukier with the Hotel Chelsea (Getty, Patrick McMullan/Getty)
Chelsea Hotel owners sue city for $100M over renovation delays
Chelsea Hotel owners sue city for $100M over renovation delays
RSA's Joseph Strasburg and Judge Lawrence Marks (Getty, Strasburg via Jeffersons Siegel)
Landlord group challenges state eviction ban
Landlord group challenges state eviction ban
Redfin CEO Glenn Kelman (Getty, Redfin)
Pocket listings exclude minority homebuyers, Redfin CEO says
Pocket listings exclude minority homebuyers, Redfin CEO says
(378 West End, 300 West and 567 Ocean Avenue, Getty)
April was best month for new condo sales in 5 years
April was best month for new condo sales in 5 years
arrow_forward_ios

The Deal's newsletters give you the latest scoops, fresh headlines, marketing data, and things to know within the industry.

Loading...