Fulton Street Transit Center opening delayed (again)

Testing delays and unfinished elevators push back completion 60 to 90 days

TRD New York /
Jun.June 24, 2014 01:10 PM

The opening of Lower Manhattan’s soaring Fulton Street Transit Center, scheduled for this Thursday, has been pushed back an additional 60 to 90 days.

The megaproject is delayed thanks to testing delays and unfinished elevators, transit officials said during a Monday board meeting. Already years late and millions over budget, the hub will eventually link 11 different subway lines at six different stations, joining with the Port Authority’s World Trade Center Transportation Hub by 2016.

The MTA’s No. 7 train extension to the Far West Side of Manhattan is delayed as well, slowed by elevator issues and other problems at the 34th Street and Eleventh Avenue station. That project was scheduled to open by the end of this year, but will not be completed before February 2015 even with a newly accelerated timeline, engineering consultant Darlene Rivera told board members in the Monday meeting.

Engineers are also struggling to repair eight high-speed ventilation fans along the No. 7 line extension, according to the Times. The fans, which are designed to push hundreds of thousands of cubic feet of air per minute, currently are vibrating during tests — an issue officials are attempting to evaluate and correct. [NYT]Julie Strickland


Related Articles

arrow_forward_ios
From left: 1800 and 1815 Park Avenue, MTA's Second Avenue Subway plan, and 160 East 125th Street between 3rd and Lexington (Credit: Google Maps)

Second Ave subway’s next phase could impact Durst, Extell dev sites

Second Ave subway’s next phase could impact Durst, Extell dev sites
Corey Johnson’s MTA reform plan targets controversial Scaffold Law

Corey Johnson’s MTA reform plan targets controversial Scaffold Law

Corey Johnson’s MTA reform plan targets controversial Scaffold Law
MTA renews 50K sf at Forest City’s 1 Pierrepont Plaza in Brooklyn

MTA renews 50K sf at Forest City’s
1 Pierrepont Plaza in Brooklyn

MTA renews 50K sf at Forest City’s
1 Pierrepont Plaza in Brooklyn
The MTA is still spending millions to maintain its empty headquarters

The MTA is still spending millions to maintain its empty headquarters

The MTA is still spending millions to maintain its empty headquarters
De Blasio to Cuomo: You’ve got the money, now fix MTA and NYCHA

De Blasio to Cuomo: You’ve got the money, now fix MTA and NYCHA

De Blasio to Cuomo: You’ve got the money, now fix MTA and NYCHA
From left: RFR Holding's Aby Rosen, Gov. Andrew Cuomo, RXR Realty's Scott Rechler. (Credit: TRD, Pat Arnow, Getty Images, Pixabay)

Cuomo made appointments to state boards. Then, in apparent defiance of his own executive order, he cashed their checks

Cuomo made appointments to state boards. Then, in apparent defiance of his own executive order, he cashed their checks
To pay for the broken MTA, Cuomo wants to tax landlords near new subway projects

To pay for the broken MTA, Cuomo wants to tax landlords near new subway projects

To pay for the broken MTA, Cuomo wants to tax landlords near new subway projects
Real estate owners should pay for transit project costs, MTA officials say

Real estate owners should pay for transit project costs, MTA officials say

Real estate owners should pay for transit project costs, MTA officials say
arrow_forward_ios

The Deal's newsletters give you the latest scoops, fresh headlines, marketing data, and things to know within the industry.

Loading...