JDS sues 111 West 57th contractor, insurer over shoddy work and “blunderbuss requests”

Developer claims poor HVAC installation led to water damage

New York /
Dec.December 15, 2020 01:20 PM
JDS Development's Michael Stern and 111 West 57th Street (JDS)

JDS Development’s Michael Stern and 111 West 57th Street (JDS)

Fool me once, shame on you; fool me twice, you’re fired — and see you in court.

That’s the approach JDS Development is taking toward a contractor once employed at 111 West 57th Street, its luxury residential skyscraper on Billionaires’ Row.

In a lawsuit filed last week in New York State Supreme Court, the developer claims contractor Copper II failed to properly install the HVAC system at Steinway Tower, blowing deadlines and causing water damage on 10 floors.

The developer is also suing the contractor’s insurer, Talisman Casualty, over $11.7 million in damage claims, and wants the court to invalidate $6.9 million of what it calls “willfully exaggerated” liens brought by Copper.

The complaint alleges that JDS first put Copper on notice in November 2018, telling the contractor it was behind schedule installing overhead piping, completing the building’s mechanical rooms and circulating water needed for the HVAC system, among other tasks.

Before landing the job, Copper was required to deliver nearly $23.5 million of surety bonds, an insurance instrument meant to protect JDS against damages or liens Copper might cause. Las Vegas-based Talisman Casualty holds the bonds.

Things came to a head in July 2019, when on three separate days, JDS documented “extensive damage” across floors 10 to 15 and 27 to 31 from water leaks Copper allegedly caused by failing to properly install the HVAC system. According to the lawsuit, the contractor agreed to a new deadline of installing the system on two residential floors per week, with work on floors 44 and below completed by Aug. 15.

But by early 2020, JDS was fed up. It fired the contractor, repaired the damage and fulfilled the rest of Copper’s contractual obligations at its own expense, according to the complaint.

In March, JDS initiated its claim on an $11.7 million bond held by Talisman. Meanwhile, Covid-19 was spreading throughout the state, and two weeks later, Gov. Andrew Cuomo ordered non-essential businesses to close — including JDS’s office.

Talisman responded to JDS’s bond claim in a letter dated March 16, allegedly making clear it was in no hurry to pay out the $11.7 million bond. According to JDS, the letter reached its shuttered New York office and “unconscionably demanded a response to blunderbuss requests” for documentation of 36 specific items related to the claim “within 20 days of receipt.”

Nine months later, the developer will be expected to produce its own receipts — $11.7 million worth — in court.

Talisman Casualty did not immediately reply to a request for comment. Copper II could not be reached. JDS Development declined to comment.

This isn’t the first time that JDS has dealt with legal issues at 111 West 57th Street. Early investor AmBase has fought in court since losing its $56 million equity investment in a 2017 foreclosure. Prior to that, webs of LLCs revealed the project’s already complex funding structure.

Meanwhile, three units in the building went into contract during the pandemic.





    Related Articles

    arrow_forward_ios
    Rotem Rosen with rendering of 126 E 57th Street (Getty, ODA Architecture)
    Rotem Rosen lands $170M construction loan for Billionaires’ Row condo
    Rotem Rosen lands $170M construction loan for Billionaires’ Row condo
    Avison Young’s Keith Caggiano and Roshan Shah with 650 Madison Avenue (Avison Young, Vornado Realty Trust, Getty)
    CRE brokers wrestle over $900K commission for 650 Madison
    CRE brokers wrestle over $900K commission for 650 Madison
    Estate Partners' David Aviram, FIA Capital Partners' David Goldwasser and Steve Croman (LinkedIn, Google Maps, Getty)
    Steve Croman: I was duped by predatory lender
    Steve Croman: I was duped by predatory lender
    From left: McSam Hotel Group's Sam Chang and SL Green's Marc Holliday with 711 Seventh Avenue  (Getty, Google Mpas, SL Green)
    Times Square hotel developer sues neighbors over delayed demolition
    Times Square hotel developer sues neighbors over delayed demolition
     Justice Sandra Sciortino and Newburgh mayor Torrance Harvey (Facebook, Daniel Case, CC BY-SA 3.0, via Wikimedia Commons)
    “Good cause eviction” struck down in Newburgh
    “Good cause eviction” struck down in Newburgh
    Rotem Rosen and Alex Sapir (Illustration by Kevin Cifuentes for The Real Deal with Getty Images)
    Sapir and Rosen settle longstanding legal feud
    Sapir and Rosen settle longstanding legal feud
    A photo illustration of Paterson Mayor Andre Sayegh along with a rendering of the planned development at 305-319 Pennsylvania Avenue (Getty, HannaBS, CC BY-SA 4.0 - via Wikimedia Commons, Paterson City Council, Google Maps)
    Judge upholds approval for 171-unit development in Paterson
    Judge upholds approval for 171-unit development in Paterson
    From left: JDS Development Group's Michael Stern and Susquehanna International Group's Tim Gong along with 111 West 57th Street (Photo Illustration by Steven Dilakian for The Real Deal with JDS, SIG China, TikTok and Kidfly182, CC BY-SA 4.0 - via Wikimedia Commons)
    TikTok investor buys twice at 111 West 57th Street
    TikTok investor buys twice at 111 West 57th Street
    arrow_forward_ios

    The Deal's newsletters give you the latest scoops, fresh headlines, marketing data, and things to know within the industry.

    Loading...