That big hole in the ground in Brooklyn’s Clinton Hill is finally getting filled in.

Two years after workers dug out the foundation of an apartment building on the corner of Grand Avenue and Fulton Street, only to have it sit dormant so long that at least one tree sprouted, construction has finally started again. A completion date is even in sight.

Contractors breaking ground on the lot this week told The Real Deal that work on the nine-story residential building is slated to wrap in about two years. That end date doubles the project’s expected lead time.

Workers at 445 Grand Ave. (Credit: Alec McCabe/The Real Deal)

Ranger Properties, the site’s developer, filed plans for 445 Grand Ave. in September 2018. In the months that followed, contractors demolished a parking lot and laid a foundation.

Then, in the fall of 2019, work came to a halt. As The Real Deal reported in September, a fallout between executives at Ranger had brought a mechanic’s lien against the property, preventing the developer from securing financing and thus blocking further construction.

The unfinished building site became an eyesore and economic dead zone in the middle of bustling Clinton Hill. Weeds sprouted alongside the tree, construction fencing sagged along half a block of Fulton Street and Grand Avenue and pedestrians have been forced to share the sidewalks with Jersey barriers. One neighbor said it was attracting rats.

The breakthrough came late last month when Ranger and co-developer KD Sagamore Capital managed to snag a $40 million loan from Scale Lending, the financing arm of Slate Property Group. That allowed the project to restart.

The lien still stands, according to Russell Wolfson, an attorney representing Ranger executive Idan Nir. Nir, listed on Ranger’s website as the firm’s vice president, filed it after the developer’s managing principal, Sheldon Stein, failed to pay him, according to a lawsuit that deals with the conflict.

To circumvent the lien’s restrictions, Wolfson said Ranger probably set aside money to cover the debt, either in an escrow account or by purchasing a bond for 110 percent of the lien. The collateral would have allowed Ranger to secure financing and restart the project.

Legally, though, the site isn’t out of the woods. Ranger filed a suit against Nir in August, demanding he remove the lien. A court appearance is scheduled for Nov. 18.





    Related Articles

    arrow_forward_ios
    A photo illustration of the proposed Lower Platte River Corridor (Getty, Plan Preserve Play NE)
    Nebraska lawmakers mull digging $1B recreation lake
    Nebraska lawmakers mull digging $1B recreation lake
    From left: Silverstein Properties CEO Marty Burger; BedRock Real Estate Partners co-founder Tracey Applebaum; Council member Julie Won; a rendering of Innovation QNS in Astoria (Getty, BedRock Real Estate Partners, New York City Council)
    Council approves Silverstein, BedRock’s $2B Innovation QNS
    Council approves Silverstein, BedRock’s $2B Innovation QNS
    Illustration of Stefan Soloviev (HaydenSoloviev, CC BY-SA 4.0, via Wikimedia Commons, Getty)
    Soloviev bets long-dormant Midtown East site in casino sweepstakes
    Soloviev bets long-dormant Midtown East site in casino sweepstakes
    CHIP's Jay Martin and HCR Commissioner RuthAnne Visnauskas (Getty)
    Lies, damn lies, and statistics: Did rent-stabilized vacancies really fall?
    Lies, damn lies, and statistics: Did rent-stabilized vacancies really fall?
    PulteGroup's Ryan R. Marshall and RedFin's Glenn Kelman (PulteGroup, RedFin, Getty)
    Wall Street is bidding up housing stocks again
    Wall Street is bidding up housing stocks again
    Empire Capital Holdings' Josh Rahmani, Hakimian Capital's Michael Hakimian, RXR's Scott Rechler and 1330 6th Avenue (Getty, Hakimian Capital, Empire Capital Holdings, 1330aofa.com)
    Empire Capital, partners close on $320M deal for 1330 Sixth Ave
    Empire Capital, partners close on $320M deal for 1330 Sixth Ave
    Silverstein Properties' Marty Burger, City Council Speaker Adrienne Adams, BedRock Real Estate's Tracey Appelbaum, City Council member Julie Won and Mayor Eric Adams with rendering of Innovation QNS (Silverstein Properties, Getty, New York City Council, Innovation QNS)
    5 lessons from Silverstein’s Astoria deal
    5 lessons from Silverstein’s Astoria deal
    Urban Commons' Salvatore G. Takoushian with Wagner at the Battery
    Urban Commons puts FiDi hotel into bankruptcy
    Urban Commons puts FiDi hotel into bankruptcy
    arrow_forward_ios

    The Deal's newsletters give you the latest scoops, fresh headlines, marketing data, and things to know within the industry.

    Loading...