This year’s storms have proven costly for the $600-plus million renovation and expansion of the Miami Beach Convention Center.

To get the center ready for the annual Art Basel extravaganza, an extra $6.9 million was added to the $619.9 million renovation budget, the Miami Herald reported. The additional money was spent on workers cleaning up damage wrought by Hurricane Irma, as well as a storm coined the “rain bomb” that drenched Miami in early August.

Getting the job back on track entailed cutting out and replacing drywall and mold-proofing the building. After Irma blew off the convention center’s insulation and damaged some safety structures — like those used to support the parking lot above the center — crews had to repair the damage and install new ceiling tiles and light fixtures.

The renovation of the 60-year-old building is one of the most expensive projects ever undertaken in Miami Beach, with cost to fix damage caused by the storms bringing the total price to about $627 million.

Some of the extra costs may be covered by the project’s insurance or FEMA, according to the Herald, but most of the money being used comes from tax revenue collected around the Lincoln Road area, which encompasses the convention center.

The convention center will continue to host Art Basel for years to come. In October it decided to stay for at least five more years after Miami Beach agreed to pay $2.8 million for a new elevator and escalator at the convention center. [Miami Herald] –Amanda Rabines


Related Articles

arrow_forward_ios
Robert Finvarb and Abraham “Abie” Hidary with the site at 2534 North Miami Avenue (Koniver Stern Group)
Hidrock Properties, Robert Finvarb pay $13M for Wynwood site
Hidrock Properties, Robert Finvarb pay $13M for Wynwood site
Aventura Mayor Enid Weisman (Facebook via Weisman, Getty)
Aventura votes to require HOAs to submit critical reports within 48 hours
Aventura votes to require HOAs to submit critical reports within 48 hours
The current Miami Beach North Shore library with Mayor Dan Gelber (Google Maps, Gelber)
Miami Beach seeks buyers for city-owned development sites
Miami Beach seeks buyers for city-owned development sites
Developer David Edelstein and Robert Levine of RAL Development with the project (Getty, RAL)
David Edelstein, partner close on missing piece of Wynwood assemblage for office towers
David Edelstein, partner close on missing piece of Wynwood assemblage for office towers
David Grutman and Pharrell’s Goodtime Hotel had received nearly 30 noise violations (Carma Connected, Getty)
Too much of a good time? David Grutman and Pharrell’s Goodtime Hotel could lose entertainment permit
Too much of a good time? David Grutman and Pharrell’s Goodtime Hotel could lose entertainment permit
Related Companies Chairman Stephen Ross with One Flagler (Related, Getty)
Prayers answered? Related Companies closes on church site for planned office tower in downtown West Palm
Prayers answered? Related Companies closes on church site for planned office tower in downtown West Palm
Grover Corlew principal Mark Corlew with Bank of America Tower in Boca Raton (Grover Corlew)
Grover Corlew buys Bank of America Tower in Boca Raton for $45M
Grover Corlew buys Bank of America Tower in Boca Raton for $45M
The partially collapsed 12-story Champlain Towers South condo building (Getty)
Inside the tug-of-war over the Surfside condo site’s future
Inside the tug-of-war over the Surfside condo site’s future
arrow_forward_ios

The Deal's newsletters give you the latest scoops, fresh headlines, marketing data, and things to know within the industry.

Loading...