The Alexander Group allegedly mismanaged and then refused to complete Indian Creek Island mansion: lawsuit

North Miami Beach general contractor allegedly filed fraudulent lien and took advantage of client who was from out-of-town

Miami /
Oct.October 16, 2019 03:30 PM
30 Indian Creek Island Road and Shlomo Alexander

30 Indian Creek Island Road and Shlomo Alexander

The Alexander Group, a North Miami Beach-based general contractor specializing in modern mansions, is facing accusations of cost overruns, project delays and abandoning the work site of a luxurious, two-story residence under construction at 30 Indian Creek Island Road.

Four Palms of Indian Creek, a shell corporation owned by the offshore company Salvado Investment Corp., is suing The Alexander Group for breach of contract. The suit, filed last month in Miami-Dade Circuit Court, alleges that Four Palms lost more than $1 million as a result of the general contractor’s alleged ineptitude and misrepresented expertise.

Four Palm’s attorney Adrian Felix and The Alexander Group principals Orly and Shlomo Alexander did not return messages seeking comment.

David Haber, lawyer for The Alexander Group, said his client is a reputable contractor and that Four Palms only filed its complaint to avoid first being sued by the builder. “They owe my client hundreds of thousands of dollars and most of the damages they caused themselves,” Haber said. “We are going to vigorously defend the lawsuit and file a counterclaim against Four Palms.”

According to a May 10 construction lien against Four Palms, The Alexander Group is alleging nonpayment of $534,133 for the Indian Creek Island home. Four subcontractors also filed liens for a total of $59,375 in unpaid work.

In its lawsuit, Four Palms alleges that The Alexander Group was ill-equipped to take on a construction of the size and scope of its mansion project, which led to substantial overruns, delays and defective work. “Defendant took advantage of the fact that plaintiff’s members resided out-of-town and relied heavily on defendants (mis)represented expertise,” the lawsuit alleges. “Plaintiff, as a result, has been left to address and correct the numerous, costly defects that exist at the project.”

Four Palms and The Alexander Group entered into an agreement in April 2016 to build a 20,000-square-foot modern mansion that would not exceed a cost of $10.5 million, and agreed that the work would be substantially completed in 19 months. Construction began eights months later and the project fell behind schedule approximately a year later. Four Palms alleges that the shell work was supposed to be completed in September 2017, but wasn’t finished until between March 2018 and April 2018. Roof work that was also supposed to begin in September 2017 did not start until two months later, the lawsuit claims.

By January, when the project’s completion had been delayed for more than six months, Four Palms and The Alexander Group fought over the final punch list and the completion schedule. Meanwhile, the project was poorly done, according to the complaint. An air-conditioning room on the second floor had water leaks, there were excessive vibrations and dangerous overheating of the generator room, defective electrical work throughout the house and flooding on the northwest side of the property, Four Palms alleges.

On May 22, Four Palms notified The Alexander Group that it had defaulted on the construction contract. A week later, The Alexander Group terminated the contract and left the work site, the lawsuit claims.


Related Articles

arrow_forward_ios
The site of the Champlain Towers South collapse at 8777 Collins Avenue in Surfside, FL. with the settlement agreement (Circuit Court for Miami-Dade County, Loopnet)
Surfside collapse $1B settlement breakdown revealed
Surfside collapse $1B settlement breakdown revealed
The lot where the Champlain Towers South once stood (Getty)
Settlement in Surfside condo collapse now over $1B
Settlement in Surfside condo collapse now over $1B
Hussain Sajwani of Damac with Surfside (Wikipedia)
Damac to buy Surfside collapse site for $120M — no other bidders for property
Damac to buy Surfside collapse site for $120M — no other bidders for property
Alex and Yanina Sapir (Getty, Instagram, Illustration by Kevin Rebong for The Real Deal)
Developer Alex Sapir’s wife files for divorce, citing a “loveless” marriage
Developer Alex Sapir’s wife files for divorce, citing a “loveless” marriage
A photo illustration of the letter unit owners of Champlain Towers South in Surfside sent to the court (Getty Images, iStock)
Surfside collapse unit owners ask court to up their $83M payout
Surfside collapse unit owners ask court to up their $83M payout
 E11even's Marc Roberts and Romie Chaudhari with 60 and 90 Northeast 11th Street (Marc Roberts, Abingtonemerson, Loopnet, iStock)
Puff, puff, pass: Developers win approval for downtown Miami medical marijuana dispensary
Puff, puff, pass: Developers win approval for downtown Miami medical marijuana dispensary
Surfside collapse site (Getty)
Surfside collapse lawsuit reaches nearly $1B settlement
Surfside collapse lawsuit reaches nearly $1B settlement
DAMAC Properties' Hussain Sajwani and aerial view of Surfside Towers remaining foundation of condominium after collapse (Hussain Sajwani, Getty Images)
Surfside collapse site auction set for May 24
Surfside collapse site auction set for May 24
arrow_forward_ios

The Deal's newsletters give you the latest scoops, fresh headlines, marketing data, and things to know within the industry.

Loading...